The US District Court for the Middle District of Louisiana ordered the $750 million Bayou Bridge pipeline to halt construction within the Atchafalaya Basin when it concluded that the US Army Corps of Engineers’ environmental analysis likely violated the National Environmental Policy Act and the Clean Water Act due to the following deficiencies: the Corps did not provide sufficient explanation for how the proposed off-site mitigation would compensate for the loss of wetlands impacted by construction; and the Corps failed to sufficiently consider and address historical impacts to wetlands from past pipeline projects in the cumulative effects analysis. On appeal, however, the US Court of Appeals for the Fifth Circuit overturned the lower court.
Continue Reading Fifth Circuit Vacates Preliminary Injunction on Appeal, Allowing Bayou Bridge Pipeline to Proceed
Section 408
Federal District Court Halts Construction of Louisiana Pipeline Due to Corps’ Failure to Explain Off-Site Mitigation
This week, the U.S. District Court for the Middle District of Louisiana granted a preliminary injunction halting construction of the $750 million Bayou Bridge Pipeline. Judge Shelly D. Dick concluded that the U.S. Army Corps of Engineers, in authorizing the project, did not provide sufficient explanation for how the proposed off-site mitigation would compensate for the loss of wetlands impacted by construction. In addition, the Court found the Corps’ environmental analysis failed to sufficiently consider and address historical impacts to wetlands from similarly situated pipelines. Thus, the Court held that these deficiencies likely violated the National Environmental Policy Act (NEPA) and ordered the 162-mile oil pipeline to halt construction within the Atchafalaya Basin, a large wetland habitat for a variety of fish and wildlife species and a critical component of regulating flooding and stream recharge in the region. As we recently saw with the D.C. Circuit’s decision to vacate authorizations for the Sabal Trail Pipeline, this is another example of courts and environmental organizations relying on errors in a federal agency’s NEPA analysis to justify enjoining pipeline construction or operations.
Continue Reading Federal District Court Halts Construction of Louisiana Pipeline Due to Corps’ Failure to Explain Off-Site Mitigation

Ambitious White House Infrastructure Legislation Proposal Would Make Major Changes to Environmental Permitting and Reviews
On Monday, the Trump Administration released an ambitious legislative proposal that aims to stimulate $1.5 trillion in new infrastructure investment over the next 10 years, expedite the federal permitting process, address rural infrastructure needs, and prepare the American workforce for the future. To accomplish those goals, the proposal includes aggressive recommendations to streamline key federal environmental review and permitting processes for infrastructure projects. In addition to traditional forms of infrastructure, such as roads, bridges, and airports, the Legislative Outline for Rebuilding Infrastructure in America addresses drinking and wastewater systems, energy infrastructure, veterans’ hospitals, and Brownfields and Superfund sites.…