The US District Court for the Middle District of Louisiana ordered the $750 million Bayou Bridge pipeline to halt construction within the Atchafalaya Basin when it concluded that the US Army Corps of Engineers’ environmental analysis likely violated the National Environmental Policy Act and the Clean Water Act due to the following deficiencies: the Corps did not provide sufficient explanation for how the proposed off-site mitigation would compensate for the loss of wetlands impacted by construction; and the Corps failed to sufficiently consider and address historical impacts to wetlands from past pipeline projects in the cumulative effects analysis. On appeal, however, the US Court of Appeals for the Fifth Circuit overturned the lower court.
Continue Reading Fifth Circuit Vacates Preliminary Injunction on Appeal, Allowing Bayou Bridge Pipeline to Proceed

This week, the U.S. District Court for the Middle District of Louisiana granted a preliminary injunction halting construction of the $750 million Bayou Bridge Pipeline. Judge Shelly D. Dick concluded that the U.S. Army Corps of Engineers, in authorizing the project, did not provide sufficient explanation for how the proposed off-site mitigation would compensate for the loss of wetlands impacted by construction. In addition, the Court found the Corps’ environmental analysis failed to sufficiently consider and address historical impacts to wetlands from similarly situated pipelines. Thus, the Court held that these deficiencies likely violated the National Environmental Policy Act (NEPA) and ordered the 162-mile oil pipeline to halt construction within the Atchafalaya Basin, a large wetland habitat for a variety of fish and wildlife species and a critical component of regulating flooding and stream recharge in the region. As we recently saw with the D.C. Circuit’s decision to vacate authorizations for the Sabal Trail Pipeline, this is another example of courts and environmental organizations relying on errors in a federal agency’s NEPA analysis to justify enjoining pipeline construction or operations.
Continue Reading Federal District Court Halts Construction of Louisiana Pipeline Due to Corps’ Failure to Explain Off-Site Mitigation

In 2016, the US Fish and Wildlife Service (FWS or the Service) issued two policies on how to mitigate the impact of projects affecting fish and wildlife and natural resources: one overarching policy and one policy specific to Endangered Species Act implementation. Raising eyebrows, these mitigation policies were not limited to offsetting project impacts, but instead set a goal of improving the condition of affected resources.
Continue Reading Should Mitigation Meet a “Net Gain” Standard? USFWS is Reconsidering its Stance

A new policy directive issued earlier this week by the Department of Justice (Justice) has raised concern among regulated industry that the availability of Supplemental Environmental Projects (SEPs) in civil settlements could be severely reduced, or even largely eliminated. If the directive is applied to restrict the availability of SEPs, it would remove a useful, and at times powerful, tool routinely used by the regulated community to negotiate acceptable settlement agreements in civil enforcement actions. It could also eliminate tens of millions of dollars of annual funding of such projects—which typically benefit local communities or address niche environmental issues—currently provided through the use of SEPs in consent decrees. Because applicable policies preclude Justice from requiring parties to include SEPs in settlements, it is difficult to identify any upside in any potential narrowing or elimination of SEPs as an optional tool to assist in the resolution of civil environmental enforcement actions.
Continue Reading DOJ Directive May Squeeze the Life Out of Supplemental Environmental Projects